February 3, 2010: Public open house held for Steeles West Station design concept.
-
March 10, 2010: Public open house held for Vaughan Corporate Centre, Highway 407 and Steeles West Station to view preliminary design concepts.
-
March 25, 2010: Contract awarded for Construction Management Services to Morrison Hershfield Limited.
-
March 25, 2010: Contract awarded for the Tunnel Boring Machines Launch Shaft at Steeles West Station to HC Matcon Inc.
-
March 30, 2010: Public open house held for Finch West Station design concept.
-
April 1, 2010: Contract awarded for the Tunnel Boring Machines Launch Shaft at Sheppard West Station to Varcon Construction.
-
April 28, 2010: Second public open house held for Sheppard West, Finch West, York University and Steeles West Station to view preliminary design concepts.
-
May 6, 2010: Contract awarded for Condition Surveying and Monitoring Consultant to Trow Associates Inc.
-
June 21, 2010: Contract awarded for Fire Hall #141 (the relocation and construction of) to Trumbley and Hampton Inc.
-
June 22, 2010: Contract awarded for Advanced Enabling Works for Highway 407 Station to B. Gottardo Construction Ltd.
-
July 8, 2010: Public open house held for Sheppard West Station showing finishes and public artwork.
-
July 13, 2010: Public open house held for Highway 407 Station showing finishes and public artwork.
-
July 20, 2010: Contract awarded for York University Detour Road to Grascan Construction Ltd.
-
August 11, 2010: Contract awarded for Advanced Road Work and utilities relocation for Finch West Station to Varcon Construction.
-
September 8 – 23, 2010: TBM Naming Contest Entry Submission.
-
October 6 & 7, 2010: Public open house held for York University Station showing finishes and public artwork.
-
October 8 – 22, 2010: TBM Naming Contest Voting
-
October 27, 2010: Public open house held for Vaughan Corporate Centre Station showing finishes and public artwork.
-
October 27, 2010: Contract awarded for York University Detours Phase 2 to Grascan Construction Ltd.
-
October 28, 2010: Contract awarded for Land Surveying to J.D. Barnes Ltd and Montheith and Sutherland Ltd.
-
November 19, 2010: Contract awarded for A35-25 Sheppard West Station and the Southern Tunnels to Aecon Group Inc.
-
November 25, 2010: Public open house held for Finch West Subway Station showing finishes and public artwork. Sheppard West and York University Station were also on display.
-
December 10, 2010: Holey and Moley, and Yorkie and Torkie are the official names of the four tunnel boring machines (TBMs) that will bore and build the tunnels for the Toronto - York Spadina Subway Extension (TYSSE).
-
June 2009: Announcement of artists for station design collaboration with each station design consultants. Six individual finalists selected.
-
July 9, 2009: Awarding of the Tunnel Boring Machine Contract to Lovat Inc.
-
September 24, 2009: Toronto Transit Commission approved design concepts for Sheppard West Station and York University Station.
-
October 29, 2009: Toronto Transit Commission approved design concept for Steeles West Station.
- First construction contract for the project awarded to Belor Construction Ltd. for the Downsview Station to Wilson Yard Connection.
-
November 17, 2009: Toronto Transit Commission approved design concept for Highway 407 Station.
- Public open house held for Sheppard West Station design concept.
-
November 27, 2009: TYSSE Ground Breaking Ceremony for the Wilson Yard Connection project, officially under construction.
-
December 3, 2009: Public open house held for York University Station design concept.
-
December 4, 2009: TYSSE Construction Information Session held for contractors.
-
December 16, 2009: Toronto Transit Commission approved design concepts for the Vaughan Corporate Centre Station.
- Contract awarded for the Supply of Precast Concrete Tunnel Lining to Armtec Holdings Ltd.
-
February 2008: Initial construction contract was awarded by the Toronto Transit Commission for the Steeles Ave West Sewer relocation.
-
March 13, 2008: Federal Canadian Environment Assessment Agency (CEAA) approval received for the entire project from Transport Canada.
-
March 2008: Project controls and project management contracts approved by the Toronto Transit Commission.
-
April 1, 2008: Official “Start Date of project”. Sufficient governance agreements, approvals, staffing, contracts, funding and office space are in place to proceed to procurement of design and engineering firms and other project work.
-
April 4, 2008: York Region’s Conditions of Approval report with final alignment between Steeles Ave and Highway 407 was approved by the Ontario Ministry of Environment.
-
September 5, 2008: Federal Contribution Agreement officially signed and in effect.
-
October 23, 2008: The architecture/engineering contracts of the new station designs, were awarded to The Spadina Group Association, Arup Canada Inc, and EarthTech Canada (AECOM).
-
October 23, 2008: Awarding of principal Geo-Engineering Consultant contract to Golder Associates Ltd. and awarding of Geotechnical engineering consultant contract to Inspec-Sol Inc.
-
November 26, 2008: Awarding of Twin Tunnel Design Contract to Hatch Mott MacDonald Ltd.
-
December 18, 2008: Awarding of Geotechnical engineering consultant to Coffey Geotechnics Inc.
-
March 6, 2007: Federal Government announces a $697 million commitment to the project through the Building Canada Fund.
-
March 23, 2007: Provincial EA approval for Downsview to Steeles Ave portion of the project received by the Toronto Transit Commission and/or the City of Toronto.
-
April 2007: Provincial EA approval entitled “Response to Conditions of Approval Vaughan North-South Link Subway Alignment Optimization Report” for Steeles Ave to Vaughan Corporate Centre portion of the project received by York Region. The “Subway Optimization Report” is in response to the Ontario Ministry of the Environment (MOE) conditions of approval of November 2006.
-
July 2007: York Region’s Conditions of Approval report with final alignment between Steeles Ave and Highway 407 was submitted to Ontario Ministry of Environment.
-
October 9, 2007: Executive Task Force (ETF) established for the purpose of overseeing the development and construction of the project in Toronto and York Region. Initial meeting held.
-
December 13, 2007: Province of Ontario pledges an additional $200 million towards the cost of the project through the Move Ontario Trust.