Construction Schedule
Toronto-York Spadina Subway Extension
|
Location |
Scheduled |
Status of |
|---|---|---|
| Wilson Downsview Connection | February 2010 | Active |
| Advanced TBM Launch Shaft at Steeles W | April 2010 | Complete |
| Advanced TBM Launch Shaft at Sheppard W | May 2010 | Complete |
| Highway 407 - Enabling Works | July 2010 | Active |
| Finch West Station - Fire Station #141 | July 2010 | Active |
| Finch West Station - Road Work & Utilities | August 2010 | Active |
| York University Detours Phase 1 | September 2010 | Complete |
| York University Detours Phase 2 | November 2010 | Active |
|
Location |
Scheduled |
Status of |
|---|---|---|
| Sheppard West Station and the Southern Tunnels: includes Finch West Extraction Shaft | December 2010 | Active |
| Highway 407 Station and the Northern Tunnels : includes York University Site works, Finch West Station Traffic Management Staging, Steeles West Launch Shaft Permanent Works. |
January 2011 | Active |
| Finch West Station | June 2011 | Active |
| Vaughan Corporate Centre Station | June 2011 | Active |
| Steeles West Station | August 2011 | To be awarded |
| York University Station | October 2011 | To be awarded |
Scheduled start dates are tentative and subject to change due to weather and/or unforeseen events.
Track, Signal, Fare Collection Systems, Communications and Integrated Controls Works continue until December 2015.
Revenue Service for the extension is anticipated for late December 2015.